Trussed rafters

The roof of a small house built with light wood trusses, one at a time: 2×4 frames joined by toothed steel plates, spaced 24 in apart and bearing only on the outside walls, braced as they go up because a row of unbraced trusses falls like dominoes. Then decked, shingled, trimmed and insulated, until the eave shows every layer where wall meets roof.

Compare this approach →

What it does

Assemble repeated roof trusses into a restrained roof system.

Individual trusses need temporary and permanent restraint as the roof is erected and enclosed.

When it fits

  • Learning roof-truss arrangements, erection and the wall-to-roof junction.

The trade-offs

  • A truss that works in its own plane can remain unstable out of that plane.

Context. An educational model. Geometry, material assumptions and the reference building are described in the illustrated study.

The illustrated study

Drawing…

Most house roofs built today arrive on a truck. Each truss is a flat frame of 2×4s, cut and assembled in a factory to a drawing made for that one roof, and the crew’s job on site is to stand them up, space them, tie them down and brace them. Where a framer once cut every rafter and ceiling joist by hand, a crane now sets a truss every few minutes. The figure builds the roof of a small 24 ft (7.3 m) wide house that way, one truss at a time, and then finishes it: deck, shingles, eaves and gutters outside, ceiling and insulation inside. Use Show to take away whatever hides the part you are looking at.

A frame made of triangles

01

A trussed rafter does the work of a rafter, a ceiling joist and the wall that would otherwise hold them up in the middle. Its sloped top chords carry the roof; its bottom chord carries the ceiling and ties the two heels together so they cannot spread; and the webs between them cut the space into triangles. A triangle cannot change shape unless one of its sides changes length, so every member ends up pushed or pulled along its length rather than bent. That is why 2×4s can cross 24 ft.

Framed by hand, the same roof would typically need deeper rafters, ceiling joists that lap over a bearing wall down the middle of the building, and a day of cutting. The trusses span from outside wall to outside wall, so every wall inside is free to go anywhere, or nowhere. Step through the figure and the room underneath stays empty from start to finish. This model spans 24 ft (7.3 m); actual spans depend on the engineered truss design.

Trusses are not the only way to hold up a pitched roof, and they cost the house its attic. When the roof is complicated, or the space under it is wanted, the old ways come back:

What holds up the roof?

Decided by the span and shape of the roof · whether the attic is to be used · schedule and crane access · budget

  1. TrussesThis house

    Prefabricated frames of 2×4s joined by toothed steel plates, designed by the maker and set 24 in apart.

    Choose it when simple roofs spanning wall to wall, to 40 ft and more, with no bearing walls inside; a roof set and sheathed in a day or two; the lowest cost per square foot.

    The catch webs fill the attic: no rooms or storage unless attic trusses are ordered; designed before they are made, and never cut on site; bracing to the maker's drawings, and a crane.

    The house's trusses No. 03 →
  2. Stick-framed rafters

    Rafters cut on site from 2×8 to 2×12, bearing on the wall plates and a ridge, tied by ceiling joists.

    Choose it when roofs with hips, valleys and dormers; a usable attic or a vaulted ceiling; small jobs and additions.

    The catch skilled cutting and slower framing; spans limited by the lumber; the outward thrust must be tied, or the ridge made a beam.

    Rafters cut and raised No. 15 →
  3. SIP roof panels

    Insulated panels running from a structural ridge beam to the eave: foam and two OSB skins in one piece.

    Choose it when rooms vaulted to the roof, with no attic; a fast, airtight, insulated roof.

    The catch a ridge beam and engineering; joints that must be sealed perfectly or the skins rot; a higher price.

  4. Timber frame

    Heavy rafters or purlins on principal trusses, exposed inside, with plank decking, insulation and roofing above.

    Choose it when the structure is the architecture; long spans with few members.

    The catch costly timber and joinery; insulation goes above the deck, thickening the roof edge.

Here A simple gable 24 ft deep, no bearing wall wanted upstairs, and an attic that only holds insulation: trusses are the cheapest and fastest roof. The 14 in of blown insulation lies over their bottom chords.

The plates

02

The joints are made with connector plates: galvanized steel, usually 20 gauge (about 0.9 mm), punched so that rows of sharp teeth stand up from one face. At the factory the members are laid out in a jig and a press drives a plate into each face of every joint. Choose Heel in the figure to see one up close. The teeth grip the wood like dozens of short nails, and because there is a plate on both faces the joint carries load without twisting.

The plates are sized by the truss designer for the force in each joint. The biggest are at the heels, where the thrust of the sloping top chord turns into tension in the bottom chord, and at the peak. A loose or missing plate is a broken truss, which is why damaged trusses go back to the yard instead of up on the wall.

Shapes, and what each is for

03

The web pattern is chosen by span and by what has to happen under the roof. All five in the figure span the same 24 ft; change the truss and the whole row is rebuilt in the new pattern.

Fink
The W truss, and the common house truss. Its webs are short, so all of it can be 2×4, and of these five only the king post has fewer joints.
Howe
Vertical webs and diagonals leaning toward the middle. Under a roof load the verticals are stretched and the diagonals squeezed. More joints than a Fink, used where loads or spans are larger.
King post
One post from the peak to the middle of the bottom chord. Its panels are long, so here its chords step up to 2×6s; it suits short spans and low loads.
Scissors
The bottom chords slope up toward the middle too, at half the pitch of the roof, so the ceiling inside can be vaulted. The truss is shallower in the middle, which costs it stiffness: scissors trusses spread more at the heels than flat-bottomed ones.
Attic
Leaves a room inside the truss: the bottom chord becomes a floor, posts become knee walls, and a tie becomes the ceiling. The room cannot be crossed by webs, so the chords get much deeper and the joints much larger. Attic trusses in this model are steep, at 12:12, to create the headroom the room needs.

Why some webs are stretched and others squeezed, and how the load divides among them, is the subject of Trusses.

Which truss for this roof?

Decided by the ceiling you want under it · span and load · room in the roof · cost per truss

  1. FinkThis house

    The W-shaped house truss: four short webs, all 2×4.

    Choose it when flat ceilings under a pitched roof, 20 to 40 ft; the cheapest truss for the span.

    The catch webs fill the attic.

    Finks on the house No. 03 →
  2. Howe

    Verticals and diagonals in regular panels.

    Choose it when longer spans and heavier roofs such as tile; girder trusses that carry other trusses at their panel points.

    The catch more members and plates than a Fink at house spans.

  3. King post

    A single post from the peak to the bottom chord.

    Choose it when short spans: porches, sheds, garages; the fewest pieces.

    The catch long panels need heavier chords; limited span.

  4. Scissors

    The bottom chords rise toward the middle, giving a sloped ceiling inside.

    Choose it when a vaulted ceiling without a ridge beam.

    The catch they spread at the walls under load, so the bearings must allow for it; less depth for insulation near the peak.

  5. Attic

    A room framed into the truss: floor, kneewalls and ceiling within the triangle.

    Choose it when a room or storage in the roof, built with the roof.

    The catch steeper pitch, deeper chords, stiffer joints; the costliest truss, and the room is narrow.

Here A flat ceiling under a 6 in 12 roof across 24 ft is exactly what the Fink is for, and nothing cheaper does it.

Spacing and bearing

04

Trussed rafters usually go at 24 in (610) on centre, which suits 4 × 8 ft sheathing: every sheet edge lands on a truss. They can go farther apart, up to 4 ft (1220), if the decking can span it. They bear only on the outside walls, through the double top plate, which spreads each truss’s load to the studs below wherever it falls. Here the walls are framed at 16 in and the trusses at 24 in, and the top plate takes care of the mismatch.

At each end of the building a gable-end truss stands over the end wall. It has the same top chords as the others, but since it is supported along its whole length it needs no webs: vertical studs at 24 in fill it and carry the siding. At each heel of every other truss a hurricane tie, a strap of bent steel nailed to the truss and to the top plates, keeps the roof on the walls when wind tries to lift it.

Why trusses fall like dominoes

05

A truss is stiff in its own plane and almost floppy out of it. A 24 ft frame of 2×4s is only 1½ in (38) thick; standing on its edge it has nothing to stop it toppling but its nails. If the first truss of a row goes over, it lands on the second, and the pair on the third. When trusses collapse during construction, missing or late bracing is almost always the reason.

So the bracing goes in as the trusses go up, in a fixed order, and the figure follows it.

  1. The first truss is the hardest to hold, because there is nothing yet to tie it to. The crane holds it while it is braced, outside to stakes in the ground or, as here, inside down to the floor. Only then is it let go.
  2. Each following truss is set at 24 in and nailed to 2×4 restraints running along the top chords back to the first one. Under the usual guidance from the truss industry, these rows are at most about 10 ft (3 m) apart along the top chord for spans up to 30 ft, and closer for longer spans.
  3. Restraints alone only keep the trusses at the same spacing. The whole row can still lean together, like a stack of books. Diagonal bracing laid across the top chords locks the restraint lines into a triangulated plane.
  4. Permanent bracing stays in the finished roof: a continuous restraint along each long web that the designer marks as needing one, so it cannot buckle sideways under its compression, anchored by diagonals.
  5. The sheathing finally braces every top chord along its whole length, and the ceiling does the same for the bottom chords. The temporary restraints come off as the sheathing covers them.

Never cut a truss

06

Every member of a truss is working, and none is spare. Notching a chord or cutting out a web to fit a duct, an attic hatch or a skylight can take away the triangle that holds a joint in place, and the truss can fold under its next snow load. A truss that has to be changed needs a repair detail from the truss designer, usually extra lumber and plates fixed across the damage.

Finishing the roof

07

Once the row is braced, the roof is closed in from the bottom up, and every layer laps over the one below it so that water running down always lands on top of the next piece, never behind it.

  1. A 2×6 sub-fascia is nailed across the plumb-cut truss tails, lining them up and giving the fascia, soffit and gutter something to fix to. At the gable a ladder of 2×4 rungs, nailed through the gable sheathing into the gable-end truss, carries a fly rafter 12 in (305) out: the rake overhang.
  2. The deck goes on in 4 × 8 ft sheets from each eave, stopping 1 in (25) short of the ridge on both sides to leave a slot for air.
  3. Metal drip edge along the eaves, then underlayment rolled out from the eave up, each course lapping the one below, then drip edge up the rakes on top of it. At the eave the drip edge is under the underlayment and at the rake it is over it, so in both places water is led outward.
  4. Shingles from a starter course at the eave, each course nailed just above the butts of the one below so the nails are covered, with 5⅝ in (143) left to the weather. A ridge vent covers the slot.
  5. Fascia, a level soffit with a vent strip, and gutters hung on the fascia under the drip edge. Windows and doors go in once the roof keeps the rain off.
  6. Inside, gypsum board is screwed to the bottom chords, a baffle is fitted in every bay at the eaves, and insulation is blown in over the whole ceiling.

Shingles suit this roof: a 6 in 12 pitch sheds water well under them, and they are the cheapest roofing there is. Where snow is heavy, fire is a risk or the roof should outlast the house’s first owners, something else goes on the same deck:

What goes on the roof?

Decided by roof pitch · wind, snow, hail and fire · the weight the frame can carry · life span against first cost · the look of the region

  1. Asphalt shinglesThis house

    Glass-fibre mats soaked in asphalt and faced with mineral granules, laminated for depth, nailed over underlayment.

    Choose it when pitches of 4 in 12 and steeper, or down to 2 in 12 with doubled underlayment; the lowest first cost; any roofer can lay and repair it.

    The catch 20 to 30 years of life; storms lift shingles that are not wind-rated; never on a low slope.

    Shingles on the house No. 03 →
  2. Standing-seam metal

    Steel or aluminium panels running eave to ridge, joined by raised seams over hidden clips.

    Choose it when heavy snow, which slides off; wildfire country: it does not burn; a 40 to 70 year roof; slopes down to 3 in 12, or lower with sealed seams.

    The catch two to three times the cost of shingles; clips must let long panels move with heat; specialist installers.

  3. Concrete or clay tile

    Heavy interlocking tiles hung on battens over underlayment.

    Choose it when hot, sunny or fire-prone climates; a 50 to 100 year roof; the regional look.

    The catch three to four times the weight of shingles: the frame must be designed for it; breaks when walked on; 4 in 12 or steeper.

  4. Slate

    Split natural stone, each slate hung on copper nails and lapped over two below.

    Choose it when a roof to last a century or more; steep pitches and historic work.

    The catch the heaviest and costliest roof; skilled slaters only; brittle.

  5. Wood shakes

    Split or sawn cedar laid in overlapping courses.

    Choose it when the look, in dry or well-ventilated places away from wildfire.

    The catch combustible unless treated, and banned where wildfire is a risk; moss and rot in damp shade; 20 to 40 years with care.

Here A 6 in 12 roof sheds water well under shingles, snow on this site is moderate, and laminated asphalt costs about a third as much as standing-seam metal.

Where the roof meets the wall

08

Choose Eave to see the junction cut through the last truss, where three systems lock together: the structure, the weather skin and the insulated envelope. Read it from the inside out.

  • The bottom chord bears on the double top plate, which carries the load to the studs. The hurricane tie fastens the truss to the plates, so wind pulling up on the roof is passed down into the wall.
  • Blocking between the heels closes each bay over the wall, with holes in it for air. The baffle above it does two jobs: its lip dams the insulation, and its sheet holds a 1¾ in (44) channel open under the deck, so air from the soffit vent can run up every bay to the ridge vent. The roof deck stays cold and dry, and in snow country ice dams are less likely to form.
  • The deck, underlayment and shingles run out over the sub-fascia. The drip edge laps over the fascia and sheds into the gutter; the soffit runs back from the fascia to the wall, where it meets the housewrap, which runs up behind it to the top plate.
  • Inside, the ceiling board goes up first and the wall board butts up under its edge, so the wall board holds the ceiling’s edge up.

The weak spot is the insulation. Over the middle of the ceiling it is 14 in (355) deep. Over the wall it can only be as deep as the heel allows: with a standard heel, the top chord meets the wall just 3.9 in (100) above the top plate. That leaves about 4 in (100) of insulation over the inside face of the wall and 3 in (75) at the baffle, right where the warm room meets the cold eave. A raised heel lifts the truss at the wall line, with a short vertical web at each end, so the full depth can run out over the plates. It costs little in the factory and a lot to fix afterwards.

At the gable

09

Choose Gable, then hide the roofing and the deck. The gable-end truss arrived with its OSB already on; that sheathing meets the wall sheathing at the top plate, and the housewrap runs over both. The ladder’s rungs pass through to the gable truss, the deck runs over them out to the fly rafter, and the rake board covers its face. The same principle holds as at the eave: whatever is higher laps over whatever is lower.

The numbers

10

From the model in the figure: a 24 ft (7315) span between the outside faces of the walls, 18 in (457) overhangs, and lumber at about 500 kg/m³ with 20-gauge plates.

TrussPitchChords and websJointsWeight
Fink6:122×4 throughout790 lb (40 kg)
Howe6:122×4 throughout12115 lb (52 kg)
King post6:122×6 chords, 2×4 post4105 lb (47 kg)
Scissors6:12 over 3:122×4 throughout885 lb (40 kg)
Attic12:122×8 top, 2×10 floor, 2×6 walls9200 lb (90 kg)

Every joint has a plate on each face, so the Fink carries 14 plates. Its 74 ft (22.4 m) of 2×4 is about what two workers can lift by hand, which is why short-span trusses are often set without a crane. The attic truss is more than twice as heavy and is not.

Compare the decisions

Sources & further reading

  1. Building Component Safety Information (BCSI) Guide ↗

    Structural Building Components Association · 2025 edition

    Handling, installation, temporary restraint and permanent bracing of roof trusses.

    Handling, installing, restraining and bracing wood trusses; individual projects still require their truss design documents.