Pascal Group Inc.Back to editor

Building a house

No. 02 · From bare land to move-in, in 19 stages

In the catalog:Building a house

Drawing…

The reference house built in order on its lot, from the survey stakes to the last shovel of topsoil: the dig, the footings, walls and drain, the backfill; the frame, floor by floor, and the roof; the skin that sheds water; the services; the finishes. Step through it to see what each stage adds, who does it, what is inspected before the next can start, and which decisions it settles.

A house goes up in an order that is not a matter of habit. Each stage waits for what it will bear on, for what will brace it, and for the inspection of whatever it is about to hide. Follow those three rules from the surveyor’s first stake to the last shovel of topsoil and the nineteen stages in the figure fall into place, along with the reason a crew never does them in another order.

What bears on what

01

Load runs down, so construction runs up. The footing must be in the ground before the wall that stands on it, the wall before the sill bolted to its top, the sill before the joists that bear on it, the deck before the walls framed on it, the walls before the trusses that sit on their top plates. Nothing in the figure arrives before the thing it rests on; that is the load path built in the order it will later be used.

The ground goes first for the same reason. Before a footing is placed, the soil under it has to be known: a boring and a test pit on this lot found stiff silty clay good for 2,000 psf, groundwater about 14 ft down and frost reaching 42 in. Those three facts chose the foundation, set the footing’s width, and put its bottom 8 ft 2 in below grade, far under the frost.

What braces what: why backfill waits

02

The clearest case of a stage waiting to be braced is the backfill. Soil pushed against a basement wall presses on it like a fluid that grows heavier with depth: for a clay backfill, about 60 lb per square foot for every foot down. Over the 7 ft 4 in of soil against this wall that is roughly 1,600 lb on every foot of wall.

Backfill before the first floor is on and the wall has nothing at its top: it must stand as a cantilever off the footing, bending about 3,900 ft·lb per foot of wall at its base, right at the 4,000 ft·lb at which a plain 8 in concrete wall cracks. Wait for the slab to brace its foot and the floor deck to brace its head, and the same wall spans between them like a beam stood on end, and the bending falls to about 1,600 ft·lb, less than half. That is why the figure pours the slab and builds the deck (stages 8 and 9) before the backfill, and why the anchor bolts, set in the wet concrete a week earlier, matter: they are what ties the deck to the wall it is bracing.

Bracing runs through the frame the same way. Walls are held plumb by temporary 2×4 braces until the floor above ties their tops together; trusses are held upright by a temporary restraint and diagonals until the sheathing turns the whole roof into a stiff plane. Each temporary piece in the figure comes off exactly when something permanent takes its job.

What hides what: the hold points

03

An inspection comes just before something is buried, because afterwards no one can see it. The footing is inspected in its open forms, before the concrete hides the steel and the soil under it. The drain and coating are checked before backfill covers them; the plumbing under the slab is tested before the stone goes over it; the frame, pipes, ducts and wires are inspected together before insulation fills the walls; the insulation is checked before the board closes them. The work stops at each of these points until the inspector signs off, which is why they mark the ends of stages.

Hold pointBeforeWhat is checked
FootingThe pourDepth, width, firm undisturbed soil, steel
Foundation and drainBackfillWall, bolts, dampproofing, drain and stone
Under-slab plumbingStone and slabPipe, fall, a water or air test
Framing and rough-inInsulationStructure, connectors, holes and notches; pipes, ducts, wiring
InsulationDrywallR-values, air sealing, vapour control
FinalMoving inEverything, and the certificate of occupancy

Dry before anything that water ruins

04

A wood frame shrugs off a few days of rain; insulation, gypsum board, finished floors and wiring do not. So the building is dried in before the inside work begins: the roof sheathed and shingled, the walls wrapped, the windows and doors set into their flashing. Only then do the trades bring in what water would spoil. On the outside, by contrast, siding can wait; the wrap behind it already sheds the rain, so the cladding runs alongside the interior work rather than ahead of it.

The ground in and out

05

The figure measures its own earthwork from the surfaces it draws. Stripping the work area took about 100 cu yd of topsoil, piled behind the house. The basement hole took about 540 cu yd out of the ground, 9.3 ft deep at the uphill back and 7.0 ft at the front; its sides lie back at 1:1 because below 5 ft an unsupported trench in clay can collapse on whoever is in it. About 205 cu yd went back against the walls, in compacted lifts; the rest was spread to shape the ground or hauled away. At the end about 100 cu yd of topsoil went back on, the ground falling 6 in in the first 10 ft from the house on every side, with a swale uphill to carry the water coming down the lot round it. Cut and fill works through the same lot in detail.

Trades and the critical path

06

A house is built by a relay of trades, each handing a finished stage to the next: surveyor, excavator, foundation crew, framers, roofers, plumber, heating contractor, electrician, insulators, drywall crew, finish carpenters, painters. The stages that must wait on each other form the critical path: ground, foundation, frame, dry-in, rough-in, inspection, insulation, board, finishes. A day lost on any of them is a day lost on the house. Work off the path (the siding, the driveway, the landscaping) can slide without delaying the move-in. For this house a competent crew needs about six months; weather in the groundwork, inspections and materials are where the time goes.

Every stage

07
Before the ground is brokenKnow the land, lay the house on it, protect what stays.
  1. 01Survey and soils

    A surveyor finds the lot corners, measures the ground into contours and sets a benchmark that every height on the job is taken from. A boring and a test pit show what is under the topsoil, how much it can carry, how deep frost goes and where the water sits. With those, the house is placed, its floor height set and its foundation chosen.

    Who
    Land surveyor, Geotechnical engineer, Designer
    Takes
    2–6 weeks, mostly waiting on the permit
    Before going on
    Plans approved and the building permit issued.
    Decides
    Where on the lot does the house go, and which way does it lie? · What does the house stand on? · How does the house meet a sloping lot?
    Drawn in
    Contours and the house's floor height · Soil, frost and water decide the foundation
  2. 02Stake out

    The surveyor stakes the house's corners. Because the stakes will be dug away, the crew sets batter boards a few feet outside each corner, all at one height taken from the benchmark, and stretches strings between them on the lines of the foundation. Equal diagonals prove the rectangle is square.

    Who
    Surveyor, Excavator
    Takes
    1 day
    Before going on
    Corners and setbacks checked against the site plan.
    Drawn in
    Batter boards and strings
  3. 03Clear and protect

    Before any machine works, the site is protected: silt fence along the downhill edge, a gravel entrance so trucks do not track mud into the street, and a fence at the drip line of every tree that stays. Then the footprint is cleared, underground utilities are marked, and the topsoil is stripped and piled to be spread back at the end.

    Who
    Excavator, Utility locators
    Takes
    1–2 days
    Before going on
    Erosion controls inspected; utilities located.
    Drawn in
    Stripping the topsoil
GroundworkDig, pour and drain the substructure, deck it over, then give the soil back.
  1. 04Excavate

    The excavator digs the basement: down to the underside of the footings and 2 ft beyond the walls on every side, room to form, waterproof and drain them. Below 5 ft a trench can bury a worker, so the sides are laid back at a slope the soil can hold, benched, or shored. On this lot the uphill back is the deepest cut; the spoil is piled clear of the edge for backfill.

    Who
    Excavator
    Takes
    2–3 days
    Before going on
    Bottom checked for depth and for undisturbed, firm soil.
    Decides
    How do the sides of the dig stay up? · How does the house meet a sloping lot?
    Drawn in
    Digging the basement · Where the dirt goes
  2. 05Footings

    Forms are set on the bottom of the hole, steel bars laid in them on chairs, and a keyway formed down the middle so the wall cannot slide. Square pads go in under the future basement columns. The inspector sees the open forms and the bare soil before any concrete is poured.

    Who
    Foundation crew, Concrete supplier
    Takes
    2–3 days
    Before going on
    Footing inspection, before the pour.
    Drawn in
    How wide, how deep · Forms and steel
  3. 06Foundation walls

    Wall forms rise on the footings, tied through with steel at a set spacing; bucks frame the basement windows and sleeves leave holes for the pipes. The wall is poured in one go, anchor bolts are set in the wet concrete along the top, and the forms are stripped a day or two later.

    Who
    Foundation crew
    Takes
    4–7 days
    Before going on
    Wall height and bolt layout checked; forms stripped once the concrete has gained strength.
    Decides
    What are the basement walls made of?
    Drawn in
    Forming and pouring the wall · The other ways to stand a house
  4. 07Dampproof and drain

    The outside of the wall is coated against soil moisture, or membraned where groundwater can press on it. A perforated pipe is laid in washed stone beside the footing, wrapped in filter fabric, and run to daylight or a sump, so water around the house is led away before it can build up against the wall.

    Who
    Waterproofer, Foundation crew
    Takes
    1–2 days
    Before going on
    Foundation and drain inspection, before backfill.
    Decides
    How is water kept out of the basement?
    Drawn in
    Coating, drain and stone · The footing drain
  5. 08Under-slab work and slab

    The plumber lays the building drain under the basement floor and brings it out through the footing toward the sewer. Then come 4 in of stone, a radon vent pipe, a heavy vapour retarder and, here, rigid insulation, before the 4 in concrete slab is poured and its control joints cut.

    Who
    Plumber, Concrete finisher
    Takes
    2–3 days
    Before going on
    Under-slab plumbing tested and inspected, before the stone covers it.
    Drawn in
    The building drain · Slab layers
  6. 09Sill and first floor

    A treated sill on foam sealer is bolted down to the wall. Steel columns stand on their pads and carry the glulam girder down the middle; joists bear on sill and girder, a rim closes their ends, and the subfloor is glued and nailed on. The deck is the crew's working platform, and it braces the top of the foundation wall.

    Who
    Framers
    Takes
    3–4 days
    Decides
    What are the floors framed with?
    Drawn in
    Sill, joists and deck · The girder · The steel columns
  7. 10Backfill and rough grade

    Only now, with the slab bracing the bottom of the wall and the deck bracing the top, is soil pushed back against it. Backfill goes in layers of 8 to 12 in, each compacted, with clean material near the wall. The ground is shaped to fall away from the house on every side, and a swale uphill turns the water coming down the lot around it.

    Who
    Excavator
    Takes
    1–2 days
    Decides
    How does the house meet a sloping lot?
    Drawn in
    Backfilling in lifts · Cut, fill and the slope away
FramingWalls, floor and roof go up as one braced, tied structure.
  1. 11First-floor walls

    Walls are framed flat on the deck, headers over every opening, then sheathed, stood up, nailed down through the subfloor into the rim, and braced plumb. The doubled top plate laps every corner and tee, tying the walls into one box.

    Who
    Framers
    Takes
    3–5 days
    Decides
    What are the outside walls built of? · What keeps the walls from racking?
    Drawn in
    Framing the walls · Why the sheathing matters
  2. 12Second floor and walls

    The second floor repeats the first: rim and joists on the top plates, a subfloor deck, walls framed and raised on it. The stair opening is framed with doubled headers and trimmers before the deck goes down.

    Who
    Framers
    Takes
    4–6 days
    Drawn in
    Platform on platform · The stair opening
  3. 13Roof framing

    Trusses are craned or hand-set onto the top plates 24 in apart, each tied down with a hurricane tie and braced as it goes up, because a row of unbraced trusses falls like dominoes. Permanent bracing follows the truss maker's drawing, and the gable ends are framed and sheathed.

    Who
    Framers, Crane operator
    Takes
    3–5 days
    Before going on
    Truss bracing checked against the truss drawings.
    Decides
    What holds up the roof?
    Drawn in
    Setting the trusses · Tying them down · Rafters, the other way
Closing inShed the water, run the services, hold the heat.
  1. 14Dry in

    The roof is sheathed, its panel edges gapped and clipped, the temporary braces coming off as it goes on; then drip edge, underlayment and shingles. Housewrap laps down the walls like shingles, and windows and exterior doors are set over flashing laid in the right order, so every sheet sheds water onto the one below it. From here the house keeps the weather out, and the inside work can begin.

    Who
    Framers, Roofers
    Takes
    1–2 weeks
    Decides
    What goes on the roof? · What keeps water and air out behind the siding?
    Drawn in
    Housewrap and window flashing · Sheathing and roofing
  2. 15Rough-in

    With the frame open, the trades run everything that will hide in it. The plumber runs supply lines and the drain, waste and vent pipes; the heating contractor sets the furnace and ducts; the electrician sets the panel and boxes and pulls cable through bored studs. Each hole is drilled within limits that keep the joists and studs strong, and steel plates guard pipes and wires near the faces.

    Who
    Plumber, HVAC contractor, Electrician
    Takes
    2–3 weeks
    Before going on
    Rough-in and framing inspections; pipes pressure-tested.
    Decides
    What carries the water to the fixtures? · How is the house heated and cooled? · How does power reach the house?
    Drawn in
    Supply, drain and vent · Furnace and ducts · Service, panel and circuits
  3. 16Insulate and air-seal

    Every gap between inside and out is sealed: plates to subfloor, around windows, every hole the trades drilled. Batts fill the stud bays, foam lines the rim joists, and after the ceiling board is up, loose fill is blown deep into the attic.

    Who
    Insulation contractor
    Takes
    3–5 days
    Before going on
    Insulation inspection; later a blower-door test of airtightness.
    Decides
    What insulates the walls?
    Drawn in
    The four control layers
FinishingSkin, surfaces and ground: the house as it is lived in.
  1. 17Siding and trim

    Outside, corner boards and window casings go on first, then the siding laps up to them; soffit and fascia close the eaves, and gutters hang from the fascia. This runs alongside the inside work.

    Who
    Siding crew, Gutter installer
    Takes
    1–2 weeks
    Decides
    What is the house clad in?
    Drawn in
    The rainscreen behind the siding
  2. 18Drywall and finishes

    Gypsum board is screwed to ceilings, then walls, its joints taped and coated three times and sanded. Then the finishes: primer and paint, doors and trim, flooring, cabinets and counters, and the trades come back to set fixtures, registers, switches and outlets.

    Who
    Drywall crew, Finish carpenters, Painters, Flooring, The trades again
    Takes
    6–10 weeks
    Before going on
    Final plumbing, mechanical and electrical inspections.
    Drawn in
    Board in the house · The finished stair
  3. 19Final grade and landscape

    The stockpiled topsoil is spread back, the final grade checked to fall away from the house, downspouts led out onto splash blocks or into drains, the driveway and walks laid, and the ground seeded before it can wash. The final inspection closes the permit, and the house can be lived in.

    Who
    Excavator, Landscaper, Paving
    Takes
    1–2 weeks
    Before going on
    Final inspection and the certificate of occupancy.
    Drawn in
    The finished grade

Sources & further reading

  1. International Residential Code ↗

    International Code Council · 2024 IRC

    Chapter 1: inspections; construction requirements across foundations, framing, enclosure and services.

    Background reference for US residential construction. Local adoption and amendments vary; the illustrated model presets are not a statement of code compliance.

  2. Building Component Safety Information (BCSI) Guide ↗

    Structural Building Components Association · 2025 edition

    Erection sequence, temporary restraint and permanent bracing of roof trusses.

    Handling, installing, restraining and bracing wood trusses; individual projects still require their truss design documents.

A technical review has not yet been recorded for this entry.